Construction Planning Management involve the organization, coordination, and control of construction projects from inception to completion. To help with test preparation, you can access resources like Construction Planning and Management MCQs with answer
Which of the following is not a PERT event?
A. bus starts from Jaipur
B. class is being attended
C. site investigation started
D. sessional work completedActivity 4-5 in the network shown in Fig. 7.1 can only be initiated when
A. activity 2-4 is completed
B. activity 2-3 is completed
C. activity 2-4 and 2>-A both are com-pleted
D. activity 3-4 is completedWhich of the following is a weakness of bar chart?
A. project progress
B. uncertainties
C. interdependencies of activities
D. all of the aboveThe PERT network analysis technique is most helpful for :
A. research and development projects
B. deterministic activities
C. small projects
D. large and complex projects