Construction Planning Management involve the organization, coordination, and control of construction projects from inception to completion. To help with test preparation, you can access resources like Construction Planning and Management MCQs with answer
The period of time during which direct costs do not decrease as time increases is referred to as :
A. normal time
B. standard time
C. crash time
D. optimistic timeWhat estimate would you give for the variance in above problem?
A. 90
B. 81
C. 54
D. 22The independent float affects only :
A. succeeding activities
B. the particular activity involved
C. preceding activities
D. None of themCritical path :
A. may be longest
B. may be shortest
C. is always longest
D. is always shortestThe critical path in the network shown in Fig. (below fig) is:
A. 1-2-3-5-6
B. 1-2-4-3-5-6
C. 1-2-3-4-5-6
D. 1-2-4-5-6Latest start of an activity is always:
A. less than latest event time of preceding node
B. greater than or equal to latest event time of preceding node
C. less than or equal to latest event time of preceding node
D. equal to latest event time of preceding nodeEarliest finish of an activity is always:
A. less than or equal to earliest event time of the following node
B. greater than or equal to earliest event time of the following node
C. greater than earliest event time of the following node
D. less than earliest event time of the following nodeWhich of these are not included in the category of an activity ?
A. the office area is being cleaned
B. the invitations are being sent
C. site located
D. foundation is being dugFor the network shown in Fig., which of the following statements is incorrect ?
A. Event 7 precedes event 6.
B. Event 5 follows event 3.
C. Event 7 can occur after event 4.
D. Events 3 and 4 occur after event 2.The time estimates for activities and the possibility that they will occur in PERT analysis are as follows:
A. Beta – distribution curve
B. Poisson’s distribution curve
C. normal distribution curve
D. none of them