Construction Planning Management involve the organization, coordination, and control of construction projects from inception to completion. To help with test preparation, you can access resources like Construction Planning and Management MCQs with answer
In resources levelling :
A. cost of project is controlled
B. uniform demand of resources is achieved
C. total duration of project is reduced
D. total duration of project is increasedGrader is used mainly for ____ ?
A. shaping and trimming
B. finishing and shaping
C. finishing, shaping and trimming
D. trimming and finishingWhich one of the following is not an excavating and moving type of equipment?
A. Dump truck
B. Scraper
C. Bulldozer
D. Clam shellFor excavating utility trenches with precise control of depth, the excavation equipment used is ____ ?
A. Shovel
B. Dragline
C. Hoe
D. NoneThe basic action involved in sheep foot rolling is ____ ?
A. Tamping
B. Vibration
C. Kneading
D. PressingSensitivity analysis is a study of ____ ?
A. economics of cost and benefits of the project
B. change in output due to change in input
C. comparison of profit and loss
D. comparison of assets and liabilitiesSlack time refers to :
A. an event
B. an activity
C. both event and activity
D. None of themEconomic saving of time results by crashing :
A. costliest critical activity
B. costliest non-critical activity
C. cheapest critical activity
D. cheapest non-critical activityThe direct cost of a project with respect to normal time is :
A. zero
B. infinite
C. maximum
D. minimumThe duration that matches the lowest possible overall project cost is :
A. normal time
B. optimistic time
C. between normal time and crash time
D. crash time