If 4 men can color 48m cloth in 2 days, 6 men can color 36 m cloth in ____ .

A. 1 day
B. 2 days
C. 3/4 days
D. 1 1/2 days

The length of cloth painted by one man in one day = 48 / 4 x 2 = 6 m 

No. of days required to paint 36 m cloth by 6 men = 36 / 6 x 6 = 1 day