Which of the following power plant are put on load for maximum time ?
A. Plant with maximum operating cost
B. Operating cost does not matter
C. Plant with minimum operating cost
D. Plant with medium operating cost
Economics Of Power Generation Mcqs
A. Plant with maximum operating cost
B. Operating cost does not matter
C. Plant with minimum operating cost
D. Plant with medium operating cost
A. The peak of the load curve
B. The area under the curve
C. The ratio of area under curve to the total area of rectangle
D. The ratio of area under curve and number of hours
A. maximum demand
B. load factor
C. the average load on power system
D. number of units generated
A. Ratio of kilowatt hour consumed to 24 hours
B. Ratio of maximum demand to the connected load
C. Ratio of connected load to maximum demand
D. Ratio of average load to connected load
A. square mean load
B. square of peak load
C. average load
D. maximum demand
A. 12 P.M. to 7 P.M.
B. 7 P.M. to 9 P.M
C. 2 A.M. to 5 A.M.
D. 5 A.M. to 12 P.M.
A. the number of hours for which the particular load lasts during a day
B. total energy consumed by the load
C. the variation of load during different hours of the day
D. total number of units generated for the given demand
A. Equal to or greater than Unity
B. Less than zero
C. Geater than Unity
D. Less than Unity
A. less than zero
B. always less than unity
C. less than or greater than 1
D. always greater than 1
A. (KWh supplied in a year) / (24 × 365)
B. {(KWh supplied in a month)/(30 x 24)
C. (KWh supplied in a day)/24
D. {(KWh supplied in a day)/ 24 } × 365