A. 3
B. 15
C. 25
D. 8
Let work done by P in 1 day = p
work done by Q in 1 day =q
Work done by R in 1 day = r
p + q = 1/8 —(1)
q + r= 1/12 —(2)
p+ q+ r = 1/6 —(3)
(3) – (2) => p = 1/6 – 1/12 = 1/12
(3) – (1) => r = 1/6 – 1/8 = 1/24
p + r = 1/12 + 1/24 = 3/24 = 1/8
=> P and R will finish the work in 8 days