In resources levelling :
A. cost of project is controlled
B. uniform demand of resources is achieved
C. total duration of project is reduced
D. total duration of project is increased
Construction planning and management involve the organization, coordination, and control of construction projects from inception to completion. Construction Planning Management MCQs with answers for test preparation.
A. cost of project is controlled
B. uniform demand of resources is achieved
C. total duration of project is reduced
D. total duration of project is increased
A. shaping and trimming
B. finishing and shaping
C. finishing, shaping and trimming
D. trimming and finishing
A. Dump truck
B. Scraper
C. Bulldozer
D. Clam shell
A. Shovel
B. Dragline
C. Hoe
D. None
A. Tamping
B. Vibration
C. Kneading
D. Pressing
A. economics of cost and benefits of the project
B. change in output due to change in input
C. comparison of profit and loss
D. comparison of assets and liabilities
A. an event
B. an activity
C. both event and activity
D. None of them
A. costliest critical activity
B. costliest non-critical activity
C. cheapest critical activity
D. cheapest non-critical activity
A. zero
B. infinite
C. maximum
D. minimum
A. normal time
B. optimistic time
C. between normal time and crash time
D. crash time