A. 9.6
B. 6
C. 12
D. 23
Part of work completed by A and B in 4 days
= 4*((1/16) + (1/12))
= 7/12 C can complete 5/12th of the work in 4 days C can complete the whole job in
4÷(5/12) = 9.6 days
A. 9.6